Ohio State is in the process of revising websites and program materials to accurately reflect compliance with the law. While this work occurs, language referencing protected class status or other activities prohibited by Ohio Senate Bill 1 may still appear in some places. However, all programs and activities are being administered in compliance with federal and state law.

News

  • Slideshow: Inpatient Hospital

    Overall work on the 1.9 million-square-foot inpatient tower is 70% complete, while exterior work on the façade is nearly 85% complete. The largest single facilities project ever undertaken at Ohio State includes up to 820 beds in private-room settings, large windows to enhance patient experience, safety and training for the next generation of health care providers. The tower is scheduled to open ...
    An exterior view of the south entrance of the building
  • Slideshow: Cannon Drive Relocation Phase 2

    Construction on the Cannon Drive Relocation Phase 2 project is almost at the halfway point. At about 40% completion, between 30 and 50 workers make their way to the site daily aiming for a December 2024 completion date. Crews are currently working on opening the Herrick intersection, preparing to demolish Drake Union and continuing work on the levee. Safety remains top of mind for everyone on the...
    Cannon West sky view
  • Slideshow: Interdisciplinary Health Sciences Center

    The Interdisciplinary Health Sciences Center is about 85% complete with Hamilton Hall Phase III construction. Anatomy Phase I opened in January 2022 and Classroom Phase II opened in June 2023. In total, the $157.3 million project includes a 120,000-square-foot renovation of Hamilton Hall and construction of a new 100,000-square-foot building featuring flexible facilities to serve multiple discipl...
    Quad for the Interdisciplinary Health Sciences Center
  • Slideshow: Energy Advancement and Innovation Center

    Construction on the $49.3 million Energy Advancement and Innovation Center is about 90% complete. Crews are wrapping up seal coating on the top floors and just finished pouring the loading dock. The four-story building is on track to open at the end of November. It will be a space for Ohio State faculty members, students, alumni, ENGIE Buckeye Operations researchers, local entrepreneurs and indus...
    An exterior view of the EAIC
  • Herrick, Cannon Closures and CABS Impacts

    Updated: September 27, 2023Traffic ImpactsFrom 8 p.m. on October 4 through 5 a.m. on October 5, Herrick Drive between the Transit Hub and Lincoln Tower will be reduced to one lane, two-way traffic as roadway preparations occur for the Cannon and Herrick intersection  / Herrick bridge opening.When the intersection and Herrick bridge open at 5 a.m. on October 5, Cannon between Herrick and Lincoln T...