Ohio State is in the process of revising websites and program materials to accurately reflect compliance with the law. While this work occurs, language referencing protected class status or other activities prohibited by Ohio Senate Bill 1 may still appear in some places. However, all programs and activities are being administered in compliance with federal and state law.

News

  • Slideshow: Jane E. Heminger Hall and the Renovation of Newton Hall

    Jane E. Heminger Hall, Ohio State’s first WELL-certified building, is almost 70% complete and scheduled to open in August 2022. The first-floor renovation of Newton Hall will open the following summer. The facility is located at the corner of Neil and 9th Avenues and, when complete, will serve as a gateway to the university’s health science campus. Construction progress updates include:Inside Hem...
    Inside the three-story glass atrium, construction continues on the staircase and elliptical ramps that will connect Heminger Hall and Newton Hall.
  • Slideshow: Arts District

    Construction crews are putting the finishing touches on the Timashev Family Music Building. The building is scheduled to be completed by the end of the month with classes and programming available by Autumn 2022. Next door, work continues on the Department of Theatre, Film, and Media Arts which is approximately 40% complete. The $165.3 million Arts District is sited between 15th and 18th avenues,...
    Glass windows show a reflection of construction
  • Slideshow: Interdisciplinary Research Facility

    The Interdisciplinary Research Facility, located inside Ohio State’s Innovation District, is 57% complete. Construction updates on the five-story, 305,000 square foot building include:On the penthouse floor, exterior metal siding work is almost wrapped up, and the installation of four large air handling units is complete. A specialty exhaust system with four entropic heat wheels continues through...
    A view of the south side of the Interdisciplinary Research Facility.
  • Slideshow: Interdisciplinary Health Sciences Center

    The Interdisciplinary Health Sciences Center is 50% complete. The anatomy wing opened in January 2022. Steel installation continues as part of the classroom wing phase, and parts of Hamilton Hall are being prepared for demolition in order to expand the current building footprint. When complete, the project will create a collaborative campus for interprofessional education throughout the Health Sc...
    Structural Support for Interdisciplinary Health Sciences Center

News Archive