Ohio State is in the process of revising websites and program materials to accurately reflect compliance with the law. While this work occurs, language referencing protected class status or other activities prohibited by Ohio Senate Bill 1 may still appear in some places. However, all programs and activities are being administered in compliance with federal and state law.

News: Wexner Medical Center Inpatient Hospital

  • Slideshow: Inpatient Hospital

    Work on The Ohio State University Wexner Medical Center inpatient tower is nearing 90% complete as crews have turned over the first floor to fit-up, and are now installing furniture, medical equipment, technology, signage and art. “We’re very close to milestone two, which includes levels two, four, seven, eight and 10 being ready for fit-up,” said Kristin Poldemann, associate vice president ...
    A view of the lobby where Terrazzo floors are seen finished with a large Block O on wood near the ceiling.
  • Slideshow: Inpatient Hospital

    As crews prepare for lower-level turnover to Fit-up in mid-October, construction on The Ohio State University Wexner Medical Center Inpatient Hospital is 85% complete. Once final inspections are complete on the lower level, ground, and Level 1, the Fit-up crews will install furniture, medical equipment, technology, signage and art. “This is when we really start to see ideas coming ...
    A view of the ground floor lobby from the second floor. A large revolving door is seen with construction equipment all around the room.
  • Slideshow: Inpatient Hospital

    As more than 800 crew members make their way onto the construction site each morning, the Wexner Medical Center Inpatient Hospital construction is nearly 80% complete. Currently, crews are working to connect the ground, first and second floors from The Ohio State University Comprehensive Cancer Center – Arthur G. James Cancer Hospital and Richard J. Solove Research Institute (OSUCCC-James) to the...
    A view of the main lobby where crews are working to install flooring.
  • In the News: Columbus skyline changing with four tallest new buildings in more than 20 years

    As highlighted by The Columbus Dispatch, the Wexner Medical Center Inpatient Hospital is one of four buildings being built in Columbus that are at least 24 stories high. The four are the first new buildings in Columbus that are at least 24 stories high since 2001.The story mentions the inpatient tower’s impressive build at 26 stories and 410 feet high. It includes enough steel to construct two Ei...
    A view of the exterior of the inpatient tower from a drone.
  • City of Ohio State Podcast Season 3 Episode 1: Campus Construction

    As another outpatient care center gets approved for construction and new academic and research projects break ground, we kick off season 3 of the City of Ohio State Podcast with Kristin Poldemann, the associate vice president of Facilities Design and Construction to talk about current projects across campus. ...