  • Slideshow: Campbell Hall

    The renovation of Campbell Hall is nearing the 10% complete mark as crews continue interior work. They’ve completed removing old concrete floors from the building and are now refilling them and bringing them back up to the proper elevation. Underground plumbing is being installed on the ground floor as the penthouse roof is being removed. Historic preservation is being considered as crews work...
    A view of the front entrance of Campbell Hall
  • Slideshow: Campbell Hall

    Demolition and abatement are complete at Campbell Hall where crews are now preparing to begin Mechanical, Electrical, and Plumbing rough-ins and begin reconstruction of the interior, which includes preserving some of the original elements of the building. “We’re focusing on trying to keep some of the features of the 1916 building,” said Todd Henderly, Facilities Design and Construction (FDC)...
    A white hallway with green paint at the top and crown molding can be seen above the green.