Tagged: Wexner Medical Center Inpatient Hospital
bartholomew.185@osu.edu | October 28, 2025
A major construction milestone has been reached at the Wexner Medical Center Inpatient Hospital as the project is now at substantial completion. Hear from the teams behind the planning, design, construction and activation efforts as they prepare to open the building in early 2026. From construction to massive training simulations for more than 12,000 faculty and staff, Facilities Design and Construction (FDC) is preparing to ‘hand' the building over to the medical center to begin changing lives.
bartholomew.185@osu.edu | October 27, 2025
The Wexner Medical Center Inpatient Hospital is quickly approaching its opening date as it has reached substantial completion, marking a major milestone.
“Substantial completion means the project is essentially finished and ready to be used for its intended purpose, even if there are still several things left to finish,” said Kristin Poldemann, associate vice president of Facilities Design and Construction (FDC) on the most recent episode of the City of Ohio State Podcast.
bartholomew.185@osu.edu | October 6, 2025
As highlighted by WBNS, a 30-foot-tall Block O inside the new Ohio State University Wexner Medical Center Inpatient Hospital was lit for the first time, marking a major milestone.
The Block O is the highest on campus, sitting 365 feet above the ground. It weighs nearly three tons and contains about 750 feet of LED lighting.
mckivergan.1@osu.edu | June 26, 2025
From scale, innovation and construction updates, to how The Ohio State University Wexner Medical Center Inpatient Hospital will transform patient care across Ohio, learn more about the largest single facilities project at the university.
mckivergan.1@osu.edu | June 25, 2025
Construction on the Wexner Medical Center Inpatient Hospital is more than 95% complete as the large name sign has been installed on the 10th Ave. Garage Walkway.
“Seeing the name sign go up on the bridge was a powerful moment for everyone who has had a hand in this project,” said Ragan Fallang, Facilities Design and Construction executive project manager for the inpatient hospital. “It symbolizes how far we’ve come and how close we are to the finish line on opening this world-class facility.”
holman.126@osu.edu | June 6, 2025
The Spring 2025 edition of Ohio State’s Alumni Magazine highlighted 23 buildings on the university’s Columbus campus that were supported in part by Time and Change: The Ohio State Campaign. Capital funds from the campaign helped support the addition of new buildings and modernizing ones that have been used by Buckeyes of the past.
mckivergan.1@osu.edu | April 10, 2025
Construction on the Wexner Medical Center Inpatient Hospital is at 95% complete as crews have already turned over floors 11, 12 and 14 to the fit-up team, in addition to floors one through ten. Floors 15 and 16 are currently being turned over followed by 17 and 18. Once floors are turned over to the fit-up team, they’re cleaned and then equipment and furniture are installed.
Cabling is being installed to the operating rooms (OR) for surgical video integration which will allow medical professionals to utilize audio and video technology during procedures.
mckivergan.1@osu.edu | March 11, 2025
NBC4 recently got an inside look at The Ohio State University Wexner Medical Center Inpatient Hospital.
Wexner Medical Center Chief Clinical Officer Dr. Andrew Thomas said his team uncovered several specific needs, including more natural light throughout the building and in the patient rooms, and the need for modernized space to accomodate modern technology. The new parking garage, also a major priority in the project, was finished before tower construction began in 2020.
mckivergan.1@osu.edu | January 27, 2025
Work on The Ohio State University Wexner Medical Center Inpatient Hospital has reached 92% complete. Floors one through four and seven through 10 have been turned over to the fit-up team to install furniture, medical equipment, technology, signage and art. More than 80,000 new items, not including IT and furniture, are set to be installed over the coming months.
mckivergan.1@osu.edu | November 20, 2024
Work on The Ohio State University Wexner Medical Center inpatient tower is nearing 90% complete as crews have turned over the first floor to fit-up, and are now installing furniture, medical equipment, technology, signage and art.