Slideshow: Engineering Research and Education Laboratories

A view looking up to the observation deck from the first floor.
  • Ceiling tiles that resemble wood on the ceiling
    Ceiling panels in kitchenets on each floor that help absorb noise and reduce echo throughout the building.
  • An exterior view of the brick building from the street.
    An exterior view of the building.
  • A hallway where the left wall is brick.
    The north connector on floor four.
  • The laboratory where work stations are seen each with a storage cabinet under.
    Research laboratory on floor four.
  • A lounge with seating and tables.
    A collaboration space on floor three.
  • A view looking up to the observation deck from the first floor.
    A view from the observation deck into a laboratory.
  • A view of the basement where mechanicals can be seen.
    Pumps and mechanicals in the basement.
  • A classroom with several floor-to-ceiling windows.
    A classroom on floor three.

    Construction on the Engineering Research and Education Laboratories building has reached substantial completion and a certificate of occupancy. Final fit-out work is underway across the building, including furniture installation, punch list and pack-punch activities, and a final cleaning. Landscaping is also being finalized.

    As furniture is installed, durable lab casework constructed of metal materials, complemented by wood‑style drawer and door fronts, is being used in laboratories for equipment storage.

    Life safety testing is completed. Which included full building shutdowns to ensure emergency systems, like generators and lighting, exit signs, fire alarm devices and fire suppression systems activate properly during a power outage. These final inspections were critical to ensuring the building meets all safety and operational standards.

    Construction progress includes:

    • Final furniture installation and interior fit-out across all floors
    • Punch list and back-punch work nearing completion
    • Final cleaning of all spaces in progress
    • Landscaping and exterior site work being finalized
    • Administrative, classroom, lab and collaboration spaces fully constructed and equipped

    The project included the demolition of Watts Hall and renovates existing MacQuigg Hall. An addition will be constructed that will house research and teaching labs, collaboration spaces, offices and classroom space.