Skip to main content

College Road

The College Road rebuild supports roadway improvements, including repaving and curve adjustments east of The Oval to improve traffic flow. This section of roadway will also be redesigned to complement nearby Oval materials and aesthetics. Sidewalks will be expanded to 10 feet wide to create a more comfortable pedestrian experience. During construction, crews will also complete utility upgrades, including replacing waterlines and improving tunnel infrastructure.
 

 View Traffic Impact Map

Construction Phasing Through Spring Semester 2027

Phase 1: June 15 - Late August, College Road Northbound Only
  • College Road northbound only between Hagerty Drive and Annie and John Glenn Avenue
  • Ohio Union North and South Garages Access:
    • Use 12th Avenue to northbound College Road or High Street
  • Reduced garage entrance and exit lanes at College Road
  • College Road east sidewalk closed
  • Construction zones shift north to south during this phase
  • The CABS Campus Connector (CC) route will be detoured to southbound High Street. A temporary stop will be available on 12th Avenue south of Ohio Union. Stillman Hall and Ohio Union southbound stops will be closed.
Phase 2A: Late August - Late October, College Road Closed in Both Directions
  • College Road closed in both directions between 12th Avenue and Hagerty Drive
  • Ohio Union North and South Garages Access:
    • From the north, via southbound College Road or High Street.
    • Exiting garage traffic can proceed northbound on College Road.
  • Area sidewalk closures will occur. One side will remain open while the other is closed and detour signage will be posted.
  • CABS routes will be detoured to High Street. Temporary stops will be available for southbound traffic at High Street and 15th Avenue as well as on 12th Avenue south of Ohio Union. The Arps Hall stop will also remain open for the East Residential route.
Phase 2B: Late October  - Mid November, College Road Northbound Only
  • College Road northbound only between Hagerty Drive and Annie and John Glenn Avenue
  • Ohio Union North and South Garages Access:
    • Use 12th Avene to northbound College Road or High Street
  • College Road west sidewalk closed
  • CABS routes will be detoured to High Street. Temporary stops will be available for southbound traffic at High Street and 15th Avenue as well as on 12th Avenue south of Ohio Union. The Arps Hall stop will also remain open for the East Residential route.
Phase 3: Mid November  - Early May 2027 College Road Closed in Both Directions
  • College Road closed in both directions between Page Hall and Annie and John Glenn Avenue
  • Ohio Union North and South Garages Access:
    • Use 12th Avenue to northbound College Road or High Street
  • Area sidewalk closures will occur. One side will remain open while the other is closed and detour signage will be posted.
  • CABS routes will be detoured to High Street. Temporary stops will be available for southbound traffic at High Street and 15th Avenue as well as on 12th Avenue south of Ohio Union. The Arps Hall stop will also remain open for the East Residential route.

Project Timeline

  • 2024
  • 2025
  • 2026
  • 2027
h2

Project Team

Dan Sayer headshot

Project Manager 
Dan Sayer

Consultants
Korda/Nemeth Engineering